Summer work at Rock Creek Campus
Story by Gina Whitehill-Baziuk

At Rock Creek Campus, crews wrapped the first floor hallway in Building 7 in plastic to contain the dust from construction.Summer projects for Rock Creek are moving forward: 聽the addition to Building 7, re-striping of parking lots A and C, upgrades to the existing pond and improvements to the dust collection system for the in聽Building 2.
August 27, 2013
Written by Gina Whitehill-Baziuk
Studying can be a grind, but this week the grinding at 聽Building 7 at Rock Creek is all about the north hallway of the first floor.聽聽That explains why the hallways are wrapped in plastic to keep the dust under control.
Summer projects for Rock Creek are moving forward: 聽the addition to Building 7, re-striping of parking lots A and C, upgrades to the existing pond and improvements to the dust collection system for the Building Construction Technology Program in聽Building 2.
Crews are making progress on the new main entrance to Building 7 as the building should be fully enclosed by the end of August 鈥� just in time for cooler temps and moisture. 聽Construction is moving forward with interior framing, mechanical, electrical, and plumbing installations. Drywallers have started work on the ground floor and will move to the second floor. 聽The glass curtain wall installation is 95 percent complete. This summer crews finished renovating the existing multi-stall restrooms in the building to improve and install more efficient plumbing fixtures.
In preparation for the Building 5 work next spring, when Parking Lot B will be聽eliminated, crews are re-striping the existing parking lots (A and C) to make up for聽those lost spaces.

Crews continue work on the new glass facade of Building 7, which is slated to open next March (2014)
The existing storm water pond will be upgraded to accommodate the new buildings and聽meet current code requirements; work will begin this summer and will be completed聽by November 2013. The pond currently handles all of the storm water for the campus.
The dust collection system in the Building Construction Technology area in Building 2聽will be upgraded to meet current indoor air quality standards. This project is awaiting聽final permits and will start this summer, with the goal of completing it by the start of fall聽term.
PCC鈥檚聽2008 voter-approved聽$374 million bond program is increasing opportunities for residents to access quality, affordable higher education close to where they live and work. Additional classrooms, updated equipment and technology, and advanced workforce training programs are helping聽to pave the way for future employment options. For more information, visit聽www.pcc.edu/about/bond/about.